Big Picture: Where are we? Victors: Framing in progress, significantly behind scheduleShop: Concrete work all complete. Signing contract for build-out Corp Update We signed an 18-month lease for Pearl St. The tenants are a young couple – she’s from Pgh, he’s from elsewhere. They were living in TX, and now they’re moving back. The actual walk-throughContinue reading “Status Report, 21 Sept 2026”
Tag Archives: framing
Status Report, 7 Sept 2026
Big Picture: Where are we? Victors: Framing in progress, target to complete 9/15 (definitely going to miss)Shop: Concrete work all complete. Signing contract for build-out Corp Update One showing at Pearl St this week. Still no takers. May create a ‘promotional’ offer (i.e. give October free on an 18 month lease) At Hatfield St., we’ve hadContinue reading “Status Report, 7 Sept 2026”
Status Report, 31 Aug 2026
Big Picture: Where are we? Victors: Framing in progress, target to complete 9/15 (at risk)Shop: Concrete work all complete. Framing starts in Sept (pending framing at Victor’s) Corp Update Only one showing at Pearl St this week. Hoping this picks up in Sept as we get closer to people’s actual move date. A couple of minorContinue reading “Status Report, 31 Aug 2026”
Status Report, 24 Aug 2026
Big Picture: Where are we? Victors: Framing in progress, target to complete 9/15 (at risk)Shop: Concrete work all complete. Framing starts in Sept (pending framing at Victor’s) Corp Update I continue to have a few showings for Pearl St. Folks here definitely don’t plan far in advance- most prospective tenants are looking to move in lessContinue reading “Status Report, 24 Aug 2026”
Celebrate The Win
Last weekend we had a small gathering at Mintwood St. for the team who worked on it. A lot of people had a hand in making this a success, and we wanted them to come back and see what we had accomplished together. It was a lot of fun, and I think that particularly folksContinue reading “Celebrate The Win”
Status Report, 24 Jan 2022
Big Picture: Where are we? Inside, Trim work on third floor is complete until the doors arrive. Tile work underway in second bathroom. Sanding of stairs coming along nicely. Outside, Lots of snow this week- 12″ on the 17th, and another 4″ on the 23rd. Goals for Week of 17 Jan Complete trim work onContinue reading “Status Report, 24 Jan 2022”
Status Report, 17 Jan 2022
Big Picture: Where are we? Inside, Began tile work on second floor guest bath and also began trim work on the third floor. Outside, it’s too cold to do much other than keep it clean. Goals for Week of 10 Jan Start trim work on third floor. Should be able to complete everything that doesn’tContinue reading “Status Report, 17 Jan 2022”
Status Report, 10 Jan 2022
Big Picture: Where are we? Inside, Tile work on third floor is complete! Trim painting is underway, and we’ll start installing that next. Outside, it’s too cold to do much other than keep it clean. Goals for Week of 3 Jan Complete all tile work on third floor. Start and finish the floor, and groutContinue reading “Status Report, 10 Jan 2022”
Status Report, 03 Jan 2022
Big Picture: Where are we? Inside, We continue to work out of sequence, but progress is good. Third floor painting is complete, and tile made significant advancement. Master bath progressing also. Outside, it’s too cold to do much other than keep it clean. Goals for Week of 27 Dec Complete all tile work on thirdContinue reading “Status Report, 03 Jan 2022”
Status Report, 20 Sep 2021
Big Picture: Where are we? Inside, *INSULATION COMPLETE*. I’ll spend this week getting ready for sheetrock.Outside, Painting is complete and scaffold has been removed. We are done with the bulk of the outdoor work for a while. We will deal with landscaping, etc. in the springtime. Goals from Week of Sep 13 Painting Completed onContinue reading “Status Report, 20 Sep 2021”