Big Picture: Where are we? Victors: Framing in progress, target to complete 9/15 (at risk)Shop: Concrete work all complete. Framing starts in Sept (pending framing at Victor’s) Corp Update Only one showing at Pearl St this week. Hoping this picks up in Sept as we get closer to people’s actual move date. A couple of minorContinue reading “Status Report, 31 Aug 2026”
Tag Archives: home-improvement
Status Report, 24 Aug 2026
Big Picture: Where are we? Victors: Framing in progress, target to complete 9/15 (at risk)Shop: Concrete work all complete. Framing starts in Sept (pending framing at Victor’s) Corp Update I continue to have a few showings for Pearl St. Folks here definitely don’t plan far in advance- most prospective tenants are looking to move in lessContinue reading “Status Report, 24 Aug 2026”
A Leaky Roof No More
So I’ve mentioned in the weekly status reports that we had a significant issue with the flat roof at Mintwood. This post just shares a bit more info on that saga. When we bought the property in 2020, we knew it needed a new roof. In fact, one of the first things we did wasContinue reading “A Leaky Roof No More”
Status Report, 11 Mar 2024
Big Picture: Where are we? Block walls are completed. Next up, fences and concrete! Corp Update Goals for March
Status Report, 26 Feb 2024
Big Picture: Where are we? Fits and starts on the block walls Corp Update Goals for March