Status Report, 16 Nov 2026

Big Picture: Where are we?
Victors: Plumbing has started
Shop: Framing is 90% complete

Corp Update 

We had a busy “landlord” week. The furnace at Pearl St didn’t work, and the hot water heater at Hatfield died. The furnace was a minor maintenance issue, but the hot water tank was done. (It was 10 yrs old, so we got a full life from it.). Just a reminder to keep building capital reserves bc these things happen.

I did spend some time straightening out some questions about the shear walls by the garage door. Fortunately they were ordered through Paul Lumber, a supplier with whom I have a great working relationship. They were very accomodating of the changes. We expect to receive the panels by mid-week, so I’m hoping that they’ll get those stood up before I return from my trip.

This week I will be traveling to Portugal, so there’s a bit of “trust them to do good work”. None of the crews working right now are a problem, but I always feel better when I can be there to catch things while they’re still easy to correct.

The Shop

The shop continues to progress. This week was a lot of “smaller” things (blocking, finishing exterior layers of DensGlass, etc.). They started the stairs over the weekened, and unfortunately discovered a minor issue with how they’d framed the mezzanine, so they’ll likely spend a day cleaning that up. In the grand scheme of things, though, they continue to be very good. I’m not entirely sure they’re going to hit their Nov 30 date for watertight, but we shall see.

I’m writing this on Saturday, and the plan is that they’ll shingle the roof on Sunday. It should be one day to shingle it, and one more day to complete the flashing to tie in the ridge line to the neighbor’s building. For those who have not noticed, often when two buildings are right up against one another, they make the roof a single, continuous roof. In our case, we’re not at their roof level, but we’ll be tying into the bricks. This involves placing a piece of metal (usually aluminum, but sometimes lead) on our roof, and running it up their wall. That’s the “flashing”. After that is installed, we cut a horizontal line into the mortar of the adjacent building. We wedge a piece of aluminum or lead directly into the gap. This is called “Counterflashing”. The two pieces are independent, so that the buildings can expand and contract, but the net effect is that the narrow space between the buildings is closed off from the elements. The image below is for a metal roof, but the principles are the same.


My other big achievement this week was to resubmit the electrical plans. We got some feedback form the city about some gaps in our submitted plan. I met with the electrician, who was kind enough to walk me through various other jobs for examples. Then I spent about 10-12 hours redoing our entire submission. The electrical plan is not 20+ pages long., butI feel like we’ve nailed it this time. The gaol is to have the electrician pull service to the building as soon as the front siding is installed, so that we can use that power instead of a generator to continue the work.

My other big open item is ordering the garage door. Having gotten nowhere with smaller local shops, I’m turning to my trusty orange box store. I would have preferred to keep it local, but if they don’t return calls, there’s not much I can do.

Upcoming Tasks:

  • Frame and sheathe front wall
  • Begin siding installation
  • Coordinate with mechanical trades
  • Framing inspection and insulation

Victor’s House

The framers came back this week and knocked out almost all of the punch list items. They should wrap up the rest on Monday. The plumbers started this week, which was really big. The rough-in will take a couple of weeks, but we are pointed the right direction. Before they arrived, I went through every room in the house that has anything plumbing related. I marked up the walls and floors so they know exactly where to cut, where waste lines should run, etc. There’s a packet in each room with all of the installation dimensions from the companies that make the fixtures, so there really shouldn’t be any confusion even though I’ll be away this week.

I’m working on the coordination with the other trades (HVAC and electrical). Fortunately, since I’ve done this before, I know the sequence, and I’m pretty good about how I schedule them. They get lots of advance notice, and generally I single-thread them so they aren’t tripping over one another.

I haven’t had time to work on the porch plan yet, but that’s a “get it done this winter” item.

Next steps:

  • Build steps ( 2nd to 3rd floor). (DJS)
  • Finish window installation remediation
  • Turn on utilities once the siding is up
  • Finalize and submit plan for front porch