Status Report, 9 Nov 2026

Big Picture: Where are we?
Victors: Framing complete, roofing complete
Shop: Framing is 85% complete

Corp Update 

Weather continues to be all over the place. In the past 2 weeks, we’ve seen 80 deg and we’ve seen mid-30’s. It hasn’t been an issue so far, but we may be pressed by the time we’re putting up siding at the shop.

The mouse issue at Hatfield appears to be resolved. Certainly glad to have that behind us. New tenants have settled into Pearl St. This past weekend I pulled the window AC units out of Duncan to get ready for winter.

The Shop

Framing is coming along very nicely. When we started, the team included a couple of very experienced guys. Now that we’re into the “copy/paste” phase, we typically have 3 younger guys on site. They are still good about asking questions, though. I think my on-site presence early also helped establish that it’s 100% OK to ask me questions, which they do from time to time.

The LVL posts for the staircase finally arrived this week, so those will go up in the next couple of days. The only major missing pieces at this point are some Simpson Shear Wall assemblies and the LVL’s for the garage door area. The contractor has a group chat going for the job, so I just ping that group and a woman in their office chases the supplier to get materials on site. It actually works well to have someone in the back office who can chase materials. If the person who chases the suppliers is also working on site, they tend to get distracted by whatever else is going on that day and the phone cal doesn’t happen. This way, I know they are on top of things.

The building itself is 85% framed. Both of the “long walls” are fully built, including the 24’ high section along the garage. The main beam for the mezzanine is up. I wasn’t thrilled with their welding, so I took my own welding gear to the site and fixed it myself. it’s nice to have the skills to do things like this. The mezzanine is now framed and sheathed. The remaining portion is the front wall with the garage door, entry door, and windows. That should get knocked out this week. The roof was sheathed this weekend, and they put down ice-and-water and roof paper. Next up are shingles, more framing, and the siding.

My big open item is ordering a a garage door. I find it amazing how hard it is to get callbacks on a quote request. Aside from Home Depot, most garage dealers are small businesses, and they appear to be very hand-to-mouth. If they aren’t working when you need a door, you’ll get a call back. But if they’re busy, they don’t schedule you in the future- you have to keep calling.

Overall, I continue to be pleased with our progress at the shop. They’ll be hustling to make their 11/30 weather-tight date, but I believe they can get it done if things work out weather-wise.

Upcoming Tasks:

  • Frame front wall
  • Sheath rear wall and front wall
  • Begin siding installation
  • Begin coordination with mechanical trades
  • Install main support beam for second floor
  • Frame mezzanine. Continue framing remainder of first floor.
  • …

Victor’s House

We are finally starting to close out the rough building phase. The framers reported completion the week of Oct 19th. I then went through the building with a fine tooth comb and tagged items for correction. There were about 30 items, ranging from minor issues with easy fixes (like a few missing hurricane brackets on the roof) to complex (ex: about 5 of the windows didn’t have any sill tape under them, which is what keeps the water from getting behind the vapor barrier. That will require the removal of the exterior trim, then the removal of the window before they can install the sill tape and then re-install the window and trim.). In fairness to the framer, they didn’t put up a fuss when I pointed it out- there was some internal “WTF who did that?” but there wasn’t an attempt to wiggle out of it.

About half of the items I flagged are code compliance issues (like the brackets and the windows). It’s worth noting that the framing inspection passed even without these items. It’s a good reminder that you can’t rely on the inspector to ensure the work product. That falls to the GC/ owner. If I didn’t call these things out, they wouldn’t get fixed.

The plumbers are chomping at the bit and ready to go. They’ll start the real rough-in this week. With 4 guys full time, I’m expecting it to take about 10 working days. I need to get the HVAC guys lined up after them.

The exterior siding is nearly compete. They’l lose a few days to fixing those windows, but they should be finished this week. The shingles were also installed on the roof this past week. That means the electrician can come out shortly and pull the service line to the building. We’ll install the panel in the basement, and run at least one circuit to each floor so we have power throughout the building. That will be a huge relief- it will be nice to put away the generator and work in comparative quiet.

As we move more into the phase where I’m hands-on, I’ll be adding some apprentices to the crew. I’ve had several friends/ acquaintances reach out and express interest. Several of them have backgrounds in tech, so we have things in common. I’m not sure whether they will permanently transition into the trades or not, but it’s been a topic of discussion. I see it as living examples of the shifting job market- being college educated is no longer a guarantee of full employment, particularly for younger folks where the role can be squeezed by AI. Buildings, on the other hand, are still built by humans.

Next steps:

  • Build steps ( 1st to second floor). (DJS)
  • Complete the siding work.
  • Finish window installation remediation
  • Finish framing punch list
  • Turn on utilities once the siding is up
  • Finalize and submit plan for front porch