Status Report, 24 Aug 2026

Big Picture: Where are we? Victors: Framing in progress, target to complete 9/15 (at risk)Shop: Concrete work all complete. Framing starts in Sept (pending framing at Victor’s) Corp Update  I continue to have a few showings for Pearl St. Folks here definitely don’t plan far in advance- most prospective tenants are looking to move in lessContinue reading “Status Report, 24 Aug 2026”

Status Report, 17 Aug 2026

Big Picture: Where are we? Victors: Framing in progress, expected to complete 9/15 (still on track)Shop: Concrete work all complete. Framing starts in Sept (still on track) Corp Update  A couple of minor items working on the other properties. Had a few showings for the place on Pearl St. There are some appealing tenants from aContinue reading “Status Report, 17 Aug 2026”

Status Report, 9 Aug 2026

Big Picture: Where are we? Victors: Framing in progress, expected to complete 9/15Shop: Concrete work all complete. Framing starts in Sept OK, it’s been almost a year since I wrote a formal status report. I was doing video reports but it’s hard to capture everything in those. Also, the process of writing these helps meContinue reading “Status Report, 9 Aug 2026”

Status Report, 28 Oct 2025

Big Picture: Where are we? stuck in a holding pattern (tap-in permits) I haven’t published a written status report in quite a while- I was doing almost all video status reports. However, I’ve gotten behind, and it’s difficult to get back through everything to produce a video, so I’m doing a written report instead. (Also,Continue reading “Status Report, 28 Oct 2025”

Status Report, 26 July 2021

Big Picture: Where are we? Inside, Plumbing rough inspection is complete. We still need an electrical inspection, but that is gated on the roof repairs. (See detail below). Collecting bid & finalizing contracts for insulation and drywall. Outside, Sewer line repairs are complete. Roof repairs are scheduled for 1-14 August. Goals from Week of JuneContinue reading “Status Report, 26 July 2021”

Status Report, 19 July 2021

Big Picture: Where are we? Inside, Plumbing rough inspection is complete. We still need an electrical inspection, but that is now gated on the roof repairs. (See detail below). Outside, Sewer line repairs are complete. Roof repairs are scheduled for 1-14 August. Goals from Week of June 12 Finalize sheetrock selection Sign-off, plumbing rough inspectionContinue reading “Status Report, 19 July 2021”

Status Report, 12 July 2021

Big Picture: Where are we? Inside, We are waiting on a couple of little clean-ups on rough mechanicals, scheduled for ~12-13 July. Then we’ll be ready for pre-insulation inspection. Over the past 10 days, we’ve cleaned all of the exposed brick and repointing has begun.Outside, We have scheduled the sewer line repairs for 12-17 July.Continue reading “Status Report, 12 July 2021”

Status Report, 5 July 2021

Big Picture: Where are we? Inside, We are waiting on a couple of little clean-ups on rough mechanicals, scheduled for ~12-13 July. Then we’ll be ready for pre-insulation inspection. Over the past 10 days, we’ve cleaned all of the exposed brick and we are ready to start pointing.Outside, We have scheduled the sewer line repairsContinue reading “Status Report, 5 July 2021”