Status Report, 2 May 2021

Goals for Week of April 19 Get packed out of Orange Ave.` Accomplishments Completed pack out from Orange Ave. Movers came and picked up all of our stuff. One vault is coming to Pearl St. the week of 15 May. The other vaults will be stored in California until we’re ready for them at Mintwood.Continue reading “Status Report, 2 May 2021”

Status Report, 18 April 2021

Goals for week of April 11 As much as I can on 3rd floor railings (no progress) Head to California to pack out! (done) Sign a tenant for 580 Orange Ave. (done) Accomplishments Tenant has been selected for Orange Ave. We had a number of highly qualified applicants, and choosing the right fit was notContinue reading “Status Report, 18 April 2021”

Status Report, 11 April 2021

Goals from week of Mar 22 Finalize move date from California Install railings on 3rd floor Accomplishments Move date is locked. Packing will be April 21, and truck leaves April 22. We’ll be moving a small load to Pearl St. right away. The remainder of the Los Altos house will be in storage in CAContinue reading “Status Report, 11 April 2021”

Status Report, 4 April 2021

Goals from week of Mar 22 Framing start at Mintwood. Pearl St. railing on 3rd floor Continue to source roofing bids for Mintwood. Meet with mom to finalize the reconciliation entries in the books. Accomplishments Framing underway. Basement stairs and powder room platform complete. Footing poured for post in basement Reconciliation of books underway. Corp UpdateContinue reading “Status Report, 4 April 2021”