Status Report, 30 August 2021

Big Picture: Where are we? Inside, We failed an electrical inspection and didn’t get the HVAC inspection scheduled last week. We need to fix those before we can schedule the framing inspection we need before we can insulate.Outside, Roofing work is complete, and only painting remains. Goals from Week of Aug 16 Roofing work Completed.Continue reading “Status Report, 30 August 2021”

Status Report, 16 August 2021

Big Picture: Where are we? Inside, We’ve lined up most of the crews for final rough work after the roofing is done, but we may encounter some challenges on timing.Outside, Roofing work is well underway. Rain has slowed progress, but the crew is diligent about getting as much done each day as the weather permits.Continue reading “Status Report, 16 August 2021”

Status Report, 9 August 2021

Big Picture: Where are we? Inside, Drywall and insulation contracts are executed. We’re lining everyone up to complete rough-in inspections the week of Aug 16Outside, Roofing work did not start on Mon, Aug 2- but I’ve been reassured that they will be out Monday, Aug 9th. Goals from Week of June26 Finalize sheetrock and insulationContinue reading “Status Report, 9 August 2021”

Status Report, 2 August 2021

Big Picture: Where are we? Inside, Found contractors for insulation and drywall. We can start those after we finish rough inspections around the end of August.Outside, We built the scaffolding over the weekend, and we are ready for roof repairs starting Monday. Goals from Week of June26 Finalize sheetrock contract {selected, but he owes meContinue reading “Status Report, 2 August 2021”

Status Report, 26 July 2021

Big Picture: Where are we? Inside, Plumbing rough inspection is complete. We still need an electrical inspection, but that is gated on the roof repairs. (See detail below). Collecting bid & finalizing contracts for insulation and drywall. Outside, Sewer line repairs are complete. Roof repairs are scheduled for 1-14 August. Goals from Week of JuneContinue reading “Status Report, 26 July 2021”

Status Report, 19 July 2021

Big Picture: Where are we? Inside, Plumbing rough inspection is complete. We still need an electrical inspection, but that is now gated on the roof repairs. (See detail below). Outside, Sewer line repairs are complete. Roof repairs are scheduled for 1-14 August. Goals from Week of June 12 Finalize sheetrock selection Sign-off, plumbing rough inspectionContinue reading “Status Report, 19 July 2021”

Status Report, 12 July 2021

Big Picture: Where are we? Inside, We are waiting on a couple of little clean-ups on rough mechanicals, scheduled for ~12-13 July. Then we’ll be ready for pre-insulation inspection. Over the past 10 days, we’ve cleaned all of the exposed brick and repointing has begun.Outside, We have scheduled the sewer line repairs for 12-17 July.Continue reading “Status Report, 12 July 2021”

Status Report, 5 July 2021

Big Picture: Where are we? Inside, We are waiting on a couple of little clean-ups on rough mechanicals, scheduled for ~12-13 July. Then we’ll be ready for pre-insulation inspection. Over the past 10 days, we’ve cleaned all of the exposed brick and we are ready to start pointing.Outside, We have scheduled the sewer line repairsContinue reading “Status Report, 5 July 2021”

Status Report, 21 June 2021

OK, last week was my 25th anniversary, so there was no status report. It’s worth saying here, too, that I couldn’t be doing this crazy adventure without the support of my wife. Love you, sweetie. Thanks for everything. Big Picture: Where are we? Inside, our rough mechanicals are pretty much wrapped up. We have aContinue reading “Status Report, 21 June 2021”

Status Report, 6 June 2021

Goals for Week of May 24 FInalize roofing contract Finalize lighting plan so we can start electrical Take delivery of Mintwood plumbing fixtures Accomplishments Received plumbing fixtures. There are still a few more to order, but the key ones we need to pass rough inspection have arrived. Corp Update No update last week due to MemorialContinue reading “Status Report, 6 June 2021”