Status Report, 7 Sep 2021

Big Picture: Where are we? Inside, HVAC inspection is complete. Electrical inspection is next week.Outside, Painting progress has been a bit slower than I’d like- partially due to weather, and partially because we weren’t aligned on expectations. Addressing that now. Goals from Week of Aug 30 Painting Completed on Mintwood. {not done} Source replacement trimContinue reading “Status Report, 7 Sep 2021”

Status Report, 30 August 2021

Big Picture: Where are we? Inside, We failed an electrical inspection and didn’t get the HVAC inspection scheduled last week. We need to fix those before we can schedule the framing inspection we need before we can insulate.Outside, Roofing work is complete, and only painting remains. Goals from Week of Aug 16 Roofing work Completed.Continue reading “Status Report, 30 August 2021”

Status Report, 16 August 2021

Big Picture: Where are we? Inside, We’ve lined up most of the crews for final rough work after the roofing is done, but we may encounter some challenges on timing.Outside, Roofing work is well underway. Rain has slowed progress, but the crew is diligent about getting as much done each day as the weather permits.Continue reading “Status Report, 16 August 2021”

Status Report, 26 July 2021

Big Picture: Where are we? Inside, Plumbing rough inspection is complete. We still need an electrical inspection, but that is gated on the roof repairs. (See detail below). Collecting bid & finalizing contracts for insulation and drywall. Outside, Sewer line repairs are complete. Roof repairs are scheduled for 1-14 August. Goals from Week of JuneContinue reading “Status Report, 26 July 2021”

Status Report, 19 July 2021

Big Picture: Where are we? Inside, Plumbing rough inspection is complete. We still need an electrical inspection, but that is now gated on the roof repairs. (See detail below). Outside, Sewer line repairs are complete. Roof repairs are scheduled for 1-14 August. Goals from Week of June 12 Finalize sheetrock selection Sign-off, plumbing rough inspectionContinue reading “Status Report, 19 July 2021”

Status Report, 12 July 2021

Big Picture: Where are we? Inside, We are waiting on a couple of little clean-ups on rough mechanicals, scheduled for ~12-13 July. Then we’ll be ready for pre-insulation inspection. Over the past 10 days, we’ve cleaned all of the exposed brick and repointing has begun.Outside, We have scheduled the sewer line repairs for 12-17 July.Continue reading “Status Report, 12 July 2021”

Status Report, 5 July 2021

Big Picture: Where are we? Inside, We are waiting on a couple of little clean-ups on rough mechanicals, scheduled for ~12-13 July. Then we’ll be ready for pre-insulation inspection. Over the past 10 days, we’ve cleaned all of the exposed brick and we are ready to start pointing.Outside, We have scheduled the sewer line repairsContinue reading “Status Report, 5 July 2021”