Status Report, 13 Sep 2021

Big Picture: Where are we? Inside, *FRAMING INSPECTION COMPLETE*. We are ready to start insulation.Outside, Painting still underway. This weekend, we were supposed to adjust the scaffolds so they can work on the second floor, but that didn’t happen. This will have knock-on effects in the schedule. Goals from Week of Aug 30 Painting CompletedContinue reading “Status Report, 13 Sep 2021”

Status Report, 7 Sep 2021

Big Picture: Where are we? Inside, HVAC inspection is complete. Electrical inspection is next week.Outside, Painting progress has been a bit slower than I’d like- partially due to weather, and partially because we weren’t aligned on expectations. Addressing that now. Goals from Week of Aug 30 Painting Completed on Mintwood. {not done} Source replacement trimContinue reading “Status Report, 7 Sep 2021”

Status Report, 30 August 2021

Big Picture: Where are we? Inside, We failed an electrical inspection and didn’t get the HVAC inspection scheduled last week. We need to fix those before we can schedule the framing inspection we need before we can insulate.Outside, Roofing work is complete, and only painting remains. Goals from Week of Aug 16 Roofing work Completed.Continue reading “Status Report, 30 August 2021”

Status Report, 16 August 2021

Big Picture: Where are we? Inside, We’ve lined up most of the crews for final rough work after the roofing is done, but we may encounter some challenges on timing.Outside, Roofing work is well underway. Rain has slowed progress, but the crew is diligent about getting as much done each day as the weather permits.Continue reading “Status Report, 16 August 2021”

Communication Is Key (Roofing Update)

This week, we started work on repairing the mansards on Mintwood. I actually evaluated several different solutions, ranging from full slate replacement (too expensive) to metal roof/ simulated slate, to architectural grade shingles. In the end, we chose GAF Designer Series shingles- but not for the reason one might think. The overall bid from thisContinue reading “Communication Is Key (Roofing Update)”

Status Report, 9 August 2021

Big Picture: Where are we? Inside, Drywall and insulation contracts are executed. We’re lining everyone up to complete rough-in inspections the week of Aug 16Outside, Roofing work did not start on Mon, Aug 2- but I’ve been reassured that they will be out Monday, Aug 9th. Goals from Week of June26 Finalize sheetrock and insulationContinue reading “Status Report, 9 August 2021”

Status Report, 2 August 2021

Big Picture: Where are we? Inside, Found contractors for insulation and drywall. We can start those after we finish rough inspections around the end of August.Outside, We built the scaffolding over the weekend, and we are ready for roof repairs starting Monday. Goals from Week of June26 Finalize sheetrock contract {selected, but he owes meContinue reading “Status Report, 2 August 2021”

How To Be A Winner

OK, so it’s time to move. You’re scanning real estate listings for a rental, and starting to think about your new life. The catch is, there are other families out there going through the same process. So, how do you lock up a lease on that really great 2- bedroom you’re looking at on Zillow?Continue reading “How To Be A Winner”

Status Report, 26 July 2021

Big Picture: Where are we? Inside, Plumbing rough inspection is complete. We still need an electrical inspection, but that is gated on the roof repairs. (See detail below). Collecting bid & finalizing contracts for insulation and drywall. Outside, Sewer line repairs are complete. Roof repairs are scheduled for 1-14 August. Goals from Week of JuneContinue reading “Status Report, 26 July 2021”