Status Report, 17 Feb 2025

Big Picture: Where are we?
First round of architect sketches completed

Corp Update

  • I got my first sketches from the architect last week, and we met late in the week to review my comments. He’s working on an updated set of sketches this week. Assuming those are good, we’ll send out to a CAD technician to get formal drawings down. We will submit our plans to the city probably in the first week of March. Once I have those CAD drawings, I can also start the process of getting bids for the concrete work.

    Here’s this week’s video: https://youtu.be/nfeUVXwvqrI

    and this was last week’s, in case you missed it.
    https://youtu.be/2Gm-0Dty-e0?si=c2mLn8Zfo1n6XOLf

    Definitely subscribe to the YouTube channel so that you’re notified when I post updates!
  • Meanwhile, a few more pictures from the Arctic circle trip in January…

Next Steps:

  • Get final CAD drawings, submit to city (~March 7)
  • Begin excavation and concrete bid process (early March)