Big Picture: Where are we? Inside, New finishing team has been busy all week, and are making fantastic progress. We also removed the fireplace mantle in the dining room for repairs. Outside, No changes outside. Goals from Week of Oct 25 Get new drywall team underway. {done} Get breakers into panel and temp lights inContinue reading “Status Report, 1 Nov 2021”
Tag Archives: weekly status
Status Report, 25 Oct 2021
Big Picture: Where are we? Inside, We have terminated our relationship with the previous drywall team. Work was not up to the standard I require, and he and his crew have COVID. We are seeking out a new team to work with. Meanwhile, doing clean-up inside. Outside, No changes outside. Goals from Week of OctContinue reading “Status Report, 25 Oct 2021”
Status Report, 18 Oct 2021
Big Picture: Where are we? Inside, Drywall is 95% done, but some clean-up remains. First round of mud & tape done on 1st and 2nd floors.Outside, No changes outside. Goals from Week of Sep 27 Order trim for Mintwood. {Done} Reset expectations with drywall team. {in process} Get insurance documents out to LM {not done}Continue reading “Status Report, 18 Oct 2021”
Status Report, 11 Oct 2021
Big Picture: Where are we? Inside, Drywall is 95% done, but some clean-up remains. First round of mud & tape done on 1st and 2nd floors.Outside, No changes outside. Goals from Week of Sep 27 Get second quote for replacement trim for Mintwood. {done} Complete drywall {95%} Get insurance documents out to LM. {not done}Continue reading “Status Report, 11 Oct 2021”
Status Report, 4 Oct 2021
Big Picture: Where are we? Inside, Insulation Inspection passed and sheetrock is underway. Outside, No changes outside. Goals from Week of Sep 27 Get second quote for replacement trim for Mintwood. {underway} Get insulation approved {done} Get sheetrock underway. {underway} Accomplishments We passed our insulation inspection using the “model” approach. Sheetrock is now underway. DumpsterContinue reading “Status Report, 4 Oct 2021”
Status Report, 27 Sep 2021
Big Picture: Where are we? Inside, *INSULATION Inspection failed*. We passed for the walls, but failed the roof. Working to get this resolved this week while hoping to still move forward with sheetrock. Outside, No changes outside. Goals from Week of Sep 13 Get second quote for replacement trim for Mintwood. {Not done} Do allContinue reading “Status Report, 27 Sep 2021”
Status Report, 20 Sep 2021
Big Picture: Where are we? Inside, *INSULATION COMPLETE*. I’ll spend this week getting ready for sheetrock.Outside, Painting is complete and scaffold has been removed. We are done with the bulk of the outdoor work for a while. We will deal with landscaping, etc. in the springtime. Goals from Week of Sep 13 Painting Completed onContinue reading “Status Report, 20 Sep 2021”
Status Report, 13 Sep 2021
Big Picture: Where are we? Inside, *FRAMING INSPECTION COMPLETE*. We are ready to start insulation.Outside, Painting still underway. This weekend, we were supposed to adjust the scaffolds so they can work on the second floor, but that didn’t happen. This will have knock-on effects in the schedule. Goals from Week of Aug 30 Painting CompletedContinue reading “Status Report, 13 Sep 2021”
Status Report, 7 Sep 2021
Big Picture: Where are we? Inside, HVAC inspection is complete. Electrical inspection is next week.Outside, Painting progress has been a bit slower than I’d like- partially due to weather, and partially because we weren’t aligned on expectations. Addressing that now. Goals from Week of Aug 30 Painting Completed on Mintwood. {not done} Source replacement trimContinue reading “Status Report, 7 Sep 2021”
Status Report, 30 August 2021
Big Picture: Where are we? Inside, We failed an electrical inspection and didn’t get the HVAC inspection scheduled last week. We need to fix those before we can schedule the framing inspection we need before we can insulate.Outside, Roofing work is complete, and only painting remains. Goals from Week of Aug 16 Roofing work Completed.Continue reading “Status Report, 30 August 2021”