Status Report, 18 Oct 2021

Big Picture: Where are we? Inside, Drywall is 95% done, but some clean-up remains. First round of mud & tape done on 1st and 2nd floors.Outside, No changes outside. Goals from Week of Sep 27 Order trim for Mintwood. {Done} Reset expectations with drywall team. {in process} Get insurance documents out to LM {not done}Continue reading “Status Report, 18 Oct 2021”

Status Report, 11 Oct 2021

Big Picture: Where are we? Inside, Drywall is 95% done, but some clean-up remains. First round of mud & tape done on 1st and 2nd floors.Outside, No changes outside. Goals from Week of Sep 27 Get second quote for replacement trim for Mintwood. {done} Complete drywall {95%} Get insurance documents out to LM. {not done}Continue reading “Status Report, 11 Oct 2021”

Status Report, 4 Oct 2021

Big Picture: Where are we? Inside, Insulation Inspection passed and sheetrock is underway. Outside, No changes outside. Goals from Week of Sep 27 Get second quote for replacement trim for Mintwood. {underway} Get insulation approved {done} Get sheetrock underway. {underway} Accomplishments We passed our insulation inspection using the “model” approach. Sheetrock is now underway. DumpsterContinue reading “Status Report, 4 Oct 2021”

Status Report, 27 Sep 2021

Big Picture: Where are we? Inside, *INSULATION Inspection failed*. We passed for the walls, but failed the roof. Working to get this resolved this week while hoping to still move forward with sheetrock. Outside, No changes outside. Goals from Week of Sep 13 Get second quote for replacement trim for Mintwood. {Not done} Do allContinue reading “Status Report, 27 Sep 2021”

Status Report, 20 Sep 2021

Big Picture: Where are we? Inside, *INSULATION COMPLETE*. I’ll spend this week getting ready for sheetrock.Outside, Painting is complete and scaffold has been removed. We are done with the bulk of the outdoor work for a while. We will deal with landscaping, etc. in the springtime. Goals from Week of Sep 13 Painting Completed onContinue reading “Status Report, 20 Sep 2021”

Status Report, 13 Sep 2021

Big Picture: Where are we? Inside, *FRAMING INSPECTION COMPLETE*. We are ready to start insulation.Outside, Painting still underway. This weekend, we were supposed to adjust the scaffolds so they can work on the second floor, but that didn’t happen. This will have knock-on effects in the schedule. Goals from Week of Aug 30 Painting CompletedContinue reading “Status Report, 13 Sep 2021”