Big Picture: Where are we? Inside, Drywall is 95% done, but some clean-up remains. First round of mud & tape done on 1st and 2nd floors.Outside, No changes outside. Goals from Week of Sep 27 Get second quote for replacement trim for Mintwood. {done} Complete drywall {95%} Get insurance documents out to LM. {not done}Continue reading “Status Report, 11 Oct 2021”
Tag Archives: door trim
Status Report, 4 Oct 2021
Big Picture: Where are we? Inside, Insulation Inspection passed and sheetrock is underway. Outside, No changes outside. Goals from Week of Sep 27 Get second quote for replacement trim for Mintwood. {underway} Get insulation approved {done} Get sheetrock underway. {underway} Accomplishments We passed our insulation inspection using the “model” approach. Sheetrock is now underway. DumpsterContinue reading “Status Report, 4 Oct 2021”
Status Report, 27 Sep 2021
Big Picture: Where are we? Inside, *INSULATION Inspection failed*. We passed for the walls, but failed the roof. Working to get this resolved this week while hoping to still move forward with sheetrock. Outside, No changes outside. Goals from Week of Sep 13 Get second quote for replacement trim for Mintwood. {Not done} Do allContinue reading “Status Report, 27 Sep 2021”
Status Report, 20 Sep 2021
Big Picture: Where are we? Inside, *INSULATION COMPLETE*. I’ll spend this week getting ready for sheetrock.Outside, Painting is complete and scaffold has been removed. We are done with the bulk of the outdoor work for a while. We will deal with landscaping, etc. in the springtime. Goals from Week of Sep 13 Painting Completed onContinue reading “Status Report, 20 Sep 2021”
Status Report, 13 Sep 2021
Big Picture: Where are we? Inside, *FRAMING INSPECTION COMPLETE*. We are ready to start insulation.Outside, Painting still underway. This weekend, we were supposed to adjust the scaffolds so they can work on the second floor, but that didn’t happen. This will have knock-on effects in the schedule. Goals from Week of Aug 30 Painting CompletedContinue reading “Status Report, 13 Sep 2021”
Status Report, 7 Sep 2021
Big Picture: Where are we? Inside, HVAC inspection is complete. Electrical inspection is next week.Outside, Painting progress has been a bit slower than I’d like- partially due to weather, and partially because we weren’t aligned on expectations. Addressing that now. Goals from Week of Aug 30 Painting Completed on Mintwood. {not done} Source replacement trimContinue reading “Status Report, 7 Sep 2021”
Status Report, 30 August 2021
Big Picture: Where are we? Inside, We failed an electrical inspection and didn’t get the HVAC inspection scheduled last week. We need to fix those before we can schedule the framing inspection we need before we can insulate.Outside, Roofing work is complete, and only painting remains. Goals from Week of Aug 16 Roofing work Completed.Continue reading “Status Report, 30 August 2021”
Status Report, 16 August 2021
Big Picture: Where are we? Inside, We’ve lined up most of the crews for final rough work after the roofing is done, but we may encounter some challenges on timing.Outside, Roofing work is well underway. Rain has slowed progress, but the crew is diligent about getting as much done each day as the weather permits.Continue reading “Status Report, 16 August 2021”
Status Report, 9 August 2021
Big Picture: Where are we? Inside, Drywall and insulation contracts are executed. We’re lining everyone up to complete rough-in inspections the week of Aug 16Outside, Roofing work did not start on Mon, Aug 2- but I’ve been reassured that they will be out Monday, Aug 9th. Goals from Week of June26 Finalize sheetrock and insulationContinue reading “Status Report, 9 August 2021”
Status Report, 2 August 2021
Big Picture: Where are we? Inside, Found contractors for insulation and drywall. We can start those after we finish rough inspections around the end of August.Outside, We built the scaffolding over the weekend, and we are ready for roof repairs starting Monday. Goals from Week of June26 Finalize sheetrock contract {selected, but he owes meContinue reading “Status Report, 2 August 2021”