Working on a plaster project in the North Hills, while trying to get our landscaping plans approved.
Corp Update
- Developed a set of plans for new mitersaw station in the HackPgh woodworking shop. I was able to secure pricing from Allegheny Plywood that is very kind to our non-profit. Now I’ve put it out to the membership to fund this project.
- Trip to CA for the tenant change is all set.
- Duncan Landscape is now in the hands of God. We’ve planted it, and are watering it every day- just need those grass seeds to take hold. Lots of shrubs planted too, and some banks roses along the fence.
- Truck continues to do well. Hauled > 1000 lbs of drywall in the bed last week.
- We are waiting on our landscape architect to revise the plans for Mintwood, so we can resubmit to the city. Trying to walk the line between “persistent” but not “annoying”.
- I signed for that plaster job in the North Hills, so I’m working on that at the moment. The ceiling is pretty far out of flat, so this week I spent the week installing firring strips and making it flat. Next week I’m hanging drywall and starting compouding.




Goals for week of 15 May
- resubmit landscape plans to City by Friday.
- Hang ceiling drywall and get perimeter walls installed.
- Get first pass of trim cut at HackPgh
- Tax preparations
Love it
Great progress on the mitersaw station project and securing pricing from Allegheny Plywood. Good luck with the plaster project!
Eamon
Great DIY Ideas
LikeLike
Loved reading this
Great progress on the various projects! Good job on securing pricing for the mitersaw station and getting the plaster project underway. Best of luck with resubmitting the landscape plans to the City.
Eamon
Easy Landscape Gardening
LikeLike