Big Picture: Where are we? Inside, Hanging doors have all been installed. Only had one incorrect door, and they’re already producing the replacement. Bi-folds are next for installation. Third floor is *nearly* complete.Outside, it’s been warm for a few days, but we’re getting more rain next week. Corp Update Mom is scheduled to visit starting atContinue reading “Status Report, 21 Feb 2022”
Tag Archives: trim work
Status Report, 14 Feb 2022
Big Picture: Where are we? Inside, Doors arrived, so we are focusing on getting them installed. The team is also working to complete the sanding the stairs Outside, Still cold. Corp Update We hired a second employee effective Feb 1st. More hands, so hopefully this helps speed up some of the work on the stairs andContinue reading “Status Report, 14 Feb 2022”
Status Report, 31 Jan 2022
Big Picture: Where are we? Inside, Progressing on trim work. Painting is on ‘pause’ until we get some more trim up. Tilework is also paused. Outside, Less snow shoveling this week vs last week. Goals for Week of 24 Jan Complete tile work on second floor guest bathroom. {incomplete – see below} Complete stairwells –Continue reading “Status Report, 31 Jan 2022”