Big Picture: Where are we? Mintwood, Office bathroom tile is complete. We are working on grout, and various interior trim projects. Duncan, Rough plumbing is inspected. Waiting on rough electrical inspection. Corp Update Mom has been here all week, and we’re working her pretty hard. See below. Refinancing funds were received. We have paid down theContinue reading “Status Report, 14 Mar 2022”
Tag Archives: sewer
Status Report, 7 Mar 2022
Big Picture: Where are we? Mintwood, We’re nearly done with tile in the office bathroom, and continue to work on trim. Duncan, Rough plumbing and electrical are complete. Ready for inspections. Corp Update Mom arrived on Friday and we’ve already put her to work. Refinancing is closed, but we haven’t received our funds due to anContinue reading “Status Report, 7 Mar 2022”
Status Report, 28 Feb 2022
Big Picture: Where are we? Mintwood, Slower progress inside this week. Finished trim in the master vestibule and working on other trim. Splitting time with Duncan St to get the crew going there. Duncan, Demo complete, Sewer line replaced, and framing complete. Corp Update Mom is scheduled to visit starting at the beginning of March. WeContinue reading “Status Report, 28 Feb 2022”