Status Report, 28 March 2021

Goals for week of Mar 22 Pearl St. Kitchen installation Continue to source roofing bids for Mintwood. Meet with mom to finalize the reconciliation entries in the books.  Ideally get the tax data finalized this week too. Accomplishments Major kitchen installation work completed at Pearl St. (Countertops, sink, disposal, dishwasher) Demolition completed at Mintwood. Corp UpdateContinue reading “Status Report, 28 March 2021”

Status Report, 21 March 2021

Goals from week of Mar 15 Prep Pearl St. kitchen for countertop installation Continue to work on roof repair for Mintwood via phone calls. Accomplishments Kitchen is ready for countertops. Inst All is 10am, Tuesday March 23.  Continuing to schedule roofing inspections.  Received first actual bid and setting up additional inspections for next week. Corp UpdateContinue reading “Status Report, 21 March 2021”