Status Report, 24 June 2024

Big Picture: Where are we? Deck framing is complete. Started work on fence at Hatfield and a few other things. Corp Update  Monday Remove last portion of Hatfield Fence. Purchase new posts and set them Tuesday Set the field (fence boards) at Hatfield.Delivery of decking material Wednesday Install deckingPossible add’l work on planter boxes (evening) ThursdayContinue reading “Status Report, 24 June 2024”

Status Report, 22 Nov 2021

Big Picture: Where are we? Inside, Plaster/drywall finishing work on 2nd and 3rd floors is complete. First floor only has the staircase remaining. Tile is down in master bathroom Outside, it’s too cold to do much other than keep it clean. Goals from Week of Nov 15 Finish all drywall/plaster work. {98% complete} Install theContinue reading “Status Report, 22 Nov 2021”

Status Report, 15 Nov 2021

Big Picture: Where are we? Inside, Plaster/drywall finishing work on 2nd and 3rd floors is complete. They just have the 1st floor remaining. We’ve started priming the walls. Furnace on 3rd floor is installed, but not connected yet. Outside, Just lots of cleanup outside. Back yard is tidy, and so is the front. Goals fromContinue reading “Status Report, 15 Nov 2021”

Status Report, 8 Nov 2021

Big Picture: Where are we? Inside, Finishing team continues to crank along. Work is exceptionally good. Mantle has been removed in DR, and will be reinstalled this week. Furnace has been installed in basement, which is just in the nick of time. It has been below freezing at night (which would be bad for theContinue reading “Status Report, 8 Nov 2021”

Status Report, 1 Nov 2021

Big Picture: Where are we? Inside, New finishing team has been busy all week, and are making fantastic progress. We also removed the fireplace mantle in the dining room for repairs. Outside, No changes outside. Goals from Week of Oct 25 Get new drywall team underway. {done} Get breakers into panel and temp lights inContinue reading “Status Report, 1 Nov 2021”

Status Report, 25 Oct 2021

Big Picture: Where are we? Inside, We have terminated our relationship with the previous drywall team. Work was not up to the standard I require, and he and his crew have COVID. We are seeking out a new team to work with. Meanwhile, doing clean-up inside. Outside, No changes outside. Goals from Week of OctContinue reading “Status Report, 25 Oct 2021”

Status Report, 18 Oct 2021

Big Picture: Where are we? Inside, Drywall is 95% done, but some clean-up remains. First round of mud & tape done on 1st and 2nd floors.Outside, No changes outside. Goals from Week of Sep 27 Order trim for Mintwood. {Done} Reset expectations with drywall team. {in process} Get insurance documents out to LM {not done}Continue reading “Status Report, 18 Oct 2021”

Status Report, 11 Oct 2021

Big Picture: Where are we? Inside, Drywall is 95% done, but some clean-up remains. First round of mud & tape done on 1st and 2nd floors.Outside, No changes outside. Goals from Week of Sep 27 Get second quote for replacement trim for Mintwood. {done} Complete drywall {95%} Get insurance documents out to LM. {not done}Continue reading “Status Report, 11 Oct 2021”

Status Report, 4 Oct 2021

Big Picture: Where are we? Inside, Insulation Inspection passed and sheetrock is underway. Outside, No changes outside. Goals from Week of Sep 27 Get second quote for replacement trim for Mintwood. {underway} Get insulation approved {done} Get sheetrock underway. {underway} Accomplishments We passed our insulation inspection using the “model” approach. Sheetrock is now underway. DumpsterContinue reading “Status Report, 4 Oct 2021”

Status Report, 27 Sep 2021

Big Picture: Where are we? Inside, *INSULATION Inspection failed*. We passed for the walls, but failed the roof. Working to get this resolved this week while hoping to still move forward with sheetrock. Outside, No changes outside. Goals from Week of Sep 13 Get second quote for replacement trim for Mintwood. {Not done} Do allContinue reading “Status Report, 27 Sep 2021”