Status Report, 15 Jan 2024

Big Picture: Where are we? The hardscape project is UNDERWAY! Technically this status report is being written on Tuesday, but that’s OK… Corp Update  Goals for January

Status Report, 8 Jan 2024

Big Picture: Where are we? Vestibule plaster work is complete, and hardscape work has begun OK, this status report is more than a bit “overdue”, but this should catch everyone up to where we are. It’s been a great holiday season, with time to visit family and friends and really enjoy the fruits of our labor. There’sContinue reading “Status Report, 8 Jan 2024”

Status Report, 29 Oct 2023

Big Picture: Where are we? When one door closes, another one opens. The concrete is still stalled… BUT big news on the doors! it’s been about 6 weeks since I wrote a status report. It isn’t for lack of activity- just not what I’d define as progress. I’ll dive into it below. Corp Update Goals forContinue reading “Status Report, 29 Oct 2023”

Status Report, 22 Nov 2021

Big Picture: Where are we? Inside, Plaster/drywall finishing work on 2nd and 3rd floors is complete. First floor only has the staircase remaining. Tile is down in master bathroom Outside, it’s too cold to do much other than keep it clean. Goals from Week of Nov 15 Finish all drywall/plaster work. {98% complete} Install theContinue reading “Status Report, 22 Nov 2021”

Status Report, 15 Nov 2021

Big Picture: Where are we? Inside, Plaster/drywall finishing work on 2nd and 3rd floors is complete. They just have the 1st floor remaining. We’ve started priming the walls. Furnace on 3rd floor is installed, but not connected yet. Outside, Just lots of cleanup outside. Back yard is tidy, and so is the front. Goals fromContinue reading “Status Report, 15 Nov 2021”

Status Report, 8 Nov 2021

Big Picture: Where are we? Inside, Finishing team continues to crank along. Work is exceptionally good. Mantle has been removed in DR, and will be reinstalled this week. Furnace has been installed in basement, which is just in the nick of time. It has been below freezing at night (which would be bad for theContinue reading “Status Report, 8 Nov 2021”

Status Report, 1 Nov 2021

Big Picture: Where are we? Inside, New finishing team has been busy all week, and are making fantastic progress. We also removed the fireplace mantle in the dining room for repairs. Outside, No changes outside. Goals from Week of Oct 25 Get new drywall team underway. {done} Get breakers into panel and temp lights inContinue reading “Status Report, 1 Nov 2021”

Status Report, 25 Oct 2021

Big Picture: Where are we? Inside, We have terminated our relationship with the previous drywall team. Work was not up to the standard I require, and he and his crew have COVID. We are seeking out a new team to work with. Meanwhile, doing clean-up inside. Outside, No changes outside. Goals from Week of OctContinue reading “Status Report, 25 Oct 2021”

Status Report, 18 Oct 2021

Big Picture: Where are we? Inside, Drywall is 95% done, but some clean-up remains. First round of mud & tape done on 1st and 2nd floors.Outside, No changes outside. Goals from Week of Sep 27 Order trim for Mintwood. {Done} Reset expectations with drywall team. {in process} Get insurance documents out to LM {not done}Continue reading “Status Report, 18 Oct 2021”